New model of B.O.T contracts to determine concession period and transfer point for building power plants
Sohel Emamiam * 1, Sayed Gholamreza JalaliNaeeni Sayed Gholamreza JalaliNaeeni , Kamran Shahnaghi
Abstract:   (4462 Views)

Abstract:

In the developing countries, there is an interest to attract investments in private and foreign sectors due to the lack of financial resource required for infrastructure projects. Build-Operate-Transfer (BOT) method is one of the approaches in which the private sector is assigned to construct the project and gains its own interest after which it transfers the project to the government. In this paper, according to the proposed case study, a method was obtained to determine the concession period length and the transfer point of project by taking into account both parties' willingness, effects of risks and uncertainty regarding the project's parameters, considering the lack of complete information at least for one party by using bargaining game theory and Monte-Carlo simulation.

Keywords: Build-Operate-Transfer (BOT), concession period, net present value, economical lifetime of the project, bi-level programming, Monte-Carlo simulation
Full-Text [PDF 1051 kb]   (1143 Downloads)    
Type of Study: Applicable | Subject: Special
Received: 2015/12/29 | Accepted: 2016/03/12 | Published: 2017/01/30
References
1. McCarthy and R. L. K. Tiong, Financial and contractual aspects of build-operate-transfer projects, S. C. Int. J. Project Management, Vol. 9, No.4, 222-227, 1991.
2. [3] Shen, L. Y., Li, H., and Li, Q. M. (2002). “Alternative concession model for build operate transfer contract projects.” J. Constr. Eng. Manage., 128(4), 326–330.
3. [4] Franks, J. (1998). Building procurement systems, Chartered Institute of Building, U.K., 29–31.
4. [5] Lee, R., and Shen, L. Y. (1998). ‘‘Overview of Chinese government policies to attract BOT investment.’’ J. Hong Kong Surveyor, 9(1), 48–52.
5. [6] Medda, F., 2007. A game theory approach for the
6. allocation of risks in transport public–private
7. partnerships. International Journal of Project Management 25 (3), 213– 218.
8. [7 ] Dong, F., Tiao-jun, X., Yang, D., 2008. Bargaining
9. games for material procurement in large-scale projects. Management Science and Engineering. ICMSE 265–270.
10. [8] Ucbenli, C. 2010. A bargaining mechanism with
11. incomplete information and its application in trilateral
12. BOT negotiations, PhD dissertation, No.3448020,
13. Columbia University
14. [9] Shen, L. Y., Bao, H. j., Wu.y. z.,and Lu, w. s. (2007).
15. Using Bargaining-Game Theory for NegotiatingConcession Period for BOT-Type Contract. J. Constr. Eng. Manage.,vol.133(5)pp. 385 392.
16. [10] Brigham, E., Ehrhardt, M., 2010. Financial Management Theory and Practice. South-Western Cengage Learning, USA.


XML   Persian Abstract   Print



Rights and permissions
Creative Commons License This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
Volume 5, Issue 2 (1-2017) Back to browse issues page